    Coach Wally Hartley PK-8

  •  

    Scope of Work

    New Building Addition

    • Middle School Classrooms
    • Library
    • Cafeteria Expansion
    • Administration

    Renovations to Hughey

    • New Roof
    • HVAC System Replacement
    • Aesthetic Upgrades to classrooms and administration

    New Playfield

  • hurricanes logo revised

  • Total Budget

    $48,670,313   

    *This total is based on an anticipated project schedule and adjusted for inflation. Project totals may change based on revised project schedules during the course of the five-year bond.

Construction Budget

  • $43,029,593

    *The Construction Cost Limitations (CCL's) for each project are the amounts left for construction once contingency and soft costs have been taken out.  Soft Costs include:  Construction Contingency, Specialty Consultants, Technology & Cabling, Furniture & Fixtures, Movers, Permits, Hazardous Materials and in some cases Portable Costs.

    Budget Breakdown