Scope of Work
New 50,000 sq.ft. Building Addition
PK-1 Classrooms
Administrative Offices
Multipurpose Room
Library
Renovations to Existing Bradley Campus
New Paint, Ceilings & Flooring-minor renovation
Repurposing of Current Administration and Library to create new classrooms
Renovation of cafeteria & Kitchen expansion/addition
Total Budget
$20,435,388
*This total is based on an anticipated project schedule and adjusted for inflation. Project totals may change based on revised project schedules during the course of the five-year bond.
Construction Budget
$18,108,551
*The Construction Cost Limitations (CCL's) for each project are the amounts left for construction once contingency and soft costs have been taken out. Soft Costs include: Construction Contingency, Specialty Consultants, Technology & Cabling, Furniture & Fixtures, Movers, Permits, Hazardous Materials and in some cases Portable Costs.